REDI construction site / Current topics / Preparatory work to begin on Kalasatama Centre, i.e. REDI, site

REDI construction site

Preparatory work to begin on Kalasatama Centre, i.e. REDI, site

Monday, October 13, 2014 - 08:45

Work preparing the way for the actual beginning of construction will start on the Kalasatama Centre, i.e. REDI, site. The preparatory work includes, among other things, small-scale earth construction work and excavations around the metro bridge.

Site activity will expand and actual construction of REDI will start when a joint venture company with the shopping centre’s investor group is formed, which is estimated to take place during October-November.

In connection with the large-scale start-up of the site, a timetable for the introduction of temporary traffic arrangements will be confirmed.

Work beginning in October 2014

Small-scale earth construction and excavation work will take place on the REDI site from the beginning of October. Work on the site will be done within restrictions outlined in decision HEL 2011-000817 (T 11 01 00 02) of the City of Helsinki Environment Centre.

Daily working hours: Work will take place Mon-Fri, 7.00-18.00 (noise level indoors <35 dB).

Blasting times Mon-Fri (if necessary, blasting may take place at other times between 7.00 and 18.00):
at 7:00–7:15        at 11:00–11:15         at 14:00–14:15         at 17:40–18:00

Impact on the environment: The preparatory work will have no impact on metro and other traffic. Noise will be measured and the results reported in accordance with the Ministry of the Environment’s guideline 1/1995 “Measurement of noise”. In excavation work and transportation of rock waste, every effort will be made to minimise dust formation, and dust collection equipment will be used in the vicinity of sensitive objects. The impact of excavation work will be measured with continuous vibration measurements. In the area of influence of excavation work, a review of neighbouring properties will be carried out before excavation begins, with the aim of monitoring the impact of the work. The review of neighbouring properties will be carried out by Kalliotekniikka Oy.

For additional information on excavation and blasting work:
Help line 040 638 6851

Additional information about REDI:
www.srv.fi/en/site/redi
www.redi.fi/en/
www.facebook.com/redibysrv

Jessi Honkanen, communications specialist, SRV, 040 652 7211, jessi.honkanen@srv.fi

At REDI, which will become the heart of the Kalasatama city district, SRV will build eight white tower buildings and the inner city’s largest shopping centre. In connection with REDI, there will also be a City of Helsinki social services and health centre as well as public thoroughfares and public utility services. The shopping centre will be completed in full in spring 2018, and the entire centre by 2022. Destia is responsible for excavation and blasting work as well as other infrastructure construction. Excavation of the underground parking area is the responsibility of SRV Infra.