REDI construction site / Current topics / The last blasting time has been brought forward

REDI construction site

The last blasting time has been brought forward

Tuesday, November 4, 2014 - 09:15

The last blasting time frame of the REDI excavation work has been brought forward because of the dark.
 
Blasting times Mon-Fri (if necessary, blasting may take place at other times between 7.00 and 18.00):
at 7:00–7:15        at 11:00–11:15         at 14:00–14:15         at 17:00–17:15